Report on Financial Assistance required under SDRF for providing drinking water
supply during the year 2015-16 / 2016-17
Hyderabad Metropolitan Water Supply & Sewerage Board (HMWSSB) is providing
drinking water of 365 MGD for the entire area of GHMC including certain villages and 4
No's of municipalities enroute. The supply meets the requirement of all State and
Central Government institutions including Defence establishments, Secunderabad
Cantonment Board etc. and industries like BHEL,ECIL, HCL etc.
Due to failure of monsoon this year (June to Till now ) water levels in Singur,
Osmansagar, Himayat sagar and Nagarjunasagar sources have considerably reduced
when compared to the last year levels as shown in the following table as on 30.11.2015.
Today's Level and
Reservoir
Full
Reservoir
Level (FTL)
in Feet
Storage
Capacity at
FTL in TMC
Level in
Feet
Osmansagar 1790.000 3.900 1757.290 0.055 1768.40 0.630
Himayatsagar 1763.500 2.967 1737.040 0.243 1753.080 1.389
Singur
Manjira 1651.750 1.500 1637.800 0.000 1646.100 0.613
Akkampally
[Krishna
Water]
1717.932
523.600 m 510.787 518.619
1675.892
29.917
245.000 m 1.499 244.600 1.396 242.450 0.926
Total 39.783 2.625 14.500
It is anticipated that there will be severe water crisis for the months of December till
next monsoon.
Bore wells which used to supplement the water requirements have likely to go dry
because of drought condition prevailing in the State. Hence, the problem will be further
compounded.
Power breakdowns, are likely to cause further dislocation of water supply services
because water supply in Hyderabad is predominantly dependent on pumping system,
since Krishna and Godavari are power dependent sources. The following contingency
plan is worked out to address the issues during the year 2015-16.
ACTION PLAN:
At Osmansagar reservoir the present level is 1757.290 ft. as on 30.11.2015. From 1-05-
2015 onwards 05.00MGD water is being drawn instead of normal 25.00 MGD with the
arrangement of Emergency pumping and it is sufficient upto 28-02-2016.
At Himayathsagar, presently 5.00 MGD is being drawn by gravity upto 31-12-2015 and
later with the arrangement of Emergency pumping and the available water is sufficient
upto 30-06-2016.
The present level in Singoor Dam is 510.787 mts and the water at 120.00 MGD was
drawn from 20.05.2015 with the arrangement of emergency pumping upto 30.11.2015.
At present only 20.00 MGD is being drawn and the available water is sufficient upto 31-
03-2016 and water from dead storage can be drawn with arrangement of secondary
pumping arrangements.
The present level in Nagarjunasagar reservoir is 509.000 ft and the water at 247.00
MGD is being drawn at present. It needs to draw water by emergency pumping
arrangement once the level touches 505.00 ft and needs secondary pumping
arrangements once the level goes beyond 500.00 ft.
Due to low levels in the reservoirs it may not be possible to provide piped water supply
to certain elevated locations and needs to provide the water through tankers.
HMWSSB will also take up repairs to the existing bore wells and convert the hand bore
wells to power bore wells wherever water is available.
HMWSSB will take up installation of static tanks at new locations where piped water
supply is not possible and alternate arrangement for water supply is required.
Power breakdowns are likely to be experienced during the year and require generators
at certain pumping houses and chlorination plants to ensure continuous pumping during
local load shedding and power breakdowns of CPDCL.
Due to depletion of water levels, water drawl from the dead storage are likely to contain
high turbidity, growth of algae, etc which may require special treatment procedures
including use of chemicals like Activated Carbon, Non-Ferric Alum etc., to address water
quality issues.
It needs diversion of Krishna/Godavari water to Manjeera system at Lingampally
reservoir premises, Hydernagar reservoir premises, at Shaikpet and other locations so as
to meet the short fall in Manjeera system.
HMWSSB
CALAMITY RELIEF PLAN FOR WATER SUPPLY DURING THE YEAR 2015-
16/2016-17
I. Transmission System
i) Osmansagar System:
a) Emergency pumping arrangements for extended period including
b) Arrangements to divert the stagnated water from pools to the pumping
area by constructing temporary bunds, channelizing with excavator
etc.,
c) Procurement of chemicals like poly Aluminium Chloride, Non- Ferric
Alum and Activated Carbon to overcome the water quality issues while
drawing the water from dead storage.
d) Arrangements for diverting Krishna water to Osmansagar system. 0.20
ii) Himayathsagar System:
a) Emergency pumping arrangements including necessary equipment. 0.20
b) Arrangements to divert the stagnated water from pools to the pumping
area by constructing temporary bunds, channelizing with excavator
etc.,
c) Procurement of chemicals like poly Aluminium Chloride, Non- Ferric
Alum and Activated Carbon to overcome the water quality issues while
drawing the water from dead storage.
d) Arrangements for diverting Krishna water to Himayathsagar system 0.20
iii) Manjeera system:
a) Erecting platform for secondary pumping arrangements including
necessary equipment.
b) Dismantling, shifting and reassembling the existing emergency
pumping equipment including all necessary mechanical and electrical
items at secondary pumping platform.
c) Arrangements to divert the stagnated water from pools to the pumping
area by constructing temporary bunds, channelizing with excavator
etc.,
d) Procurement of chemicals like poly Aluminium Chloride, Non- Ferric Alum
and Activated Carbon to overcome the water quality issues while
necessary equipment.
drawing the water from dead storage.
e) Arrangements for pumping of leaked water through gates at Singoor into
Jackwell also backwash water at Water Treatment Plants in Rajampet,
Kalabgoor and Peddapur and plugging leakages through Manjeera
Barrage.
f) Arrangements for diverting Krishna / Godavari water into Phase-III of
Manjeera system at Lingampally reservoir premises.
g) Arrangements for diverting Krishna / Godavari water into Phase-I of
Manjeera system at Lingampally reservoir premises.
h) Arrangements for diverting Krishna water into Phase-II of Manjeera
system at Hydernagar reservoir premises.
i) Arrangements for diverting Krishna water into Manjeera system at
Shaikpet Nala.
j) Arrangements for diverting Godavari water into Manjeera system at
Kukatpally by interconnecting 1800mm dia MS pipe to 700mm dia MS
pipe.
k) Arrangements for diverting Godavari water into Manjeera system at
Kukatpally by interconnecting 1800mm dia MS pipe to 800mm dia MS
pipe.
l) Arrangements for diverting Krishna water to Manjeera system from
Mailardevpally pumping station to Bahadurpura with all necessary inlet
and outlet arrangements at necessary places.
m) Arrangements for diversion of Krishna water to Manjeera system from
Prashasannagar reservoir to Thattikhana reservoir.
iv) Krishna System
a) Emergency pumping arrangements including Electrical pumping
installations, formation of Earthern bund, channelizing etc.,
b) Secondary pumping arrangements to cater to the first level
emergency pumping station once the level depletes to 500.0 ft in
Nagarjunsagar reservoir with supplying and fixing of necessary
submersible pumps, electrical panels, making sump etc.,
c) Diversion of Krishna Phase-III water to Krishna Phase II system by
linking Ring mains of both phases near Shaikpet to cater to the
areas fed by Singoor system.
d) Procurement of chemicals like poly Aluminum Chloride, Non- Ferric
Alum and Activated Carbon to overcome the water quality issues
while drawing the water from dead storage.
v) Godavari system
a) Emergency pumping arrangements including Electrical pumping
installations, formation of Earthern bund, channelizing etc.,
VI) Contingency plan to meet power breakdowns:
Providing generators at pumping stations to ensure continuous pumping
during load shedding operation / power breakdowns. 5.00
II. Distribution System
a) Transportation of water through tankers to the Ill Served areas where
piped water is not possible due to insufficient water :
b) Repairs to Hand Pumps and converting hand pump bore wells to power
bore wells where ever possible to supplement piped water supply :
c) Repairs to Static Tanks / New Installations in the areas where piped
water supply cannot be given due to insufficient water.
Total Calamity Relief Plan for 2015-16 / 2016-17 works out to Rs.134.30
Crores.